A Caffeine-Fueled Morning at Brentwood Mall Skytrain Station in Burnaby

Our crane #5044 was bright and early at Brentwood Mall Skytrain Station this morning revving up a crucial job. Onsite at 6:30 am, we were asked to help in the demolition and removal of the north stairwell, a pivotal part of the station’s renovation. Access to the site is tight, so our crane had to maneuver carefully to get to the set up area.

Our focus? Removing the staircase and landing area to make way for the station’s new look.

The challenge? Dealing with hefty pieces, the heaviest weighing between 4,000 and 5,000 lbs.

Yet armed with skill and expertise, we’re geared up to tackle the challenge head-on.

Catch us in action over the next few days, as we work diligently to reshape Brentwood Mall Skytrain Station, one step at a time. And hey, if you spot us while you’re out for a shopping spree or a quick bite, don’t hesitate to wave hello!